Conoco Phillips - Refinery Upgrades
Project Type:
Oil, Gas, Chemicals
Project Name:
Conoco Phillips - Refinery Upgrades
City:
Borger
State:
Texas
Region:
Texas Panhandle
Date Completed:
2006
Owner Name:
Conoco Phillips Cost:
$18 million
Short Description:
Austin was selected to perform construction of a delayed coker unit and a vacuum distillation unit at the Conoco Phillips Borger Refinery.
Full Description:
Austin's work scope included civil, and structural, mechanical, underground piping, and equipment erection. The work was performed on a lump sum basis with a contract value of $18 million, and our safety performance included more than 325,000 work hours with a recordable incident rate of 0.61.
Size:
325,000 work hours
Architect:
Bechtel Corporation
Business Segment:
Construction